Progress

Progress Plan

This is the initial progress plan we had at the project proposal. we gave a main priority to discussing and finalizing the project idea. Then we allocated time to learnt he software as some technologies were new to us. Since we had a lot of hardware components in our project, we allocated a time to buy all those things we need. Initially our plan was to build the hardware first and then the software. But with the time constraints and the flow, we did the opposite, building the software first and the circuit digarams, and then moving on to the physical product.

Progress Timeline

Finalizing Project Idea

Week 2 - 4

Finalized the Project Idea with the advices and comments from the supervisors.

Project Proposal

Week 5

Presented the Project proposal, complete with the problem we identified, the solution, and the basics of implementation and design. The Bill of Materials were included as well.

Project Proposal

Milestone 1

Week 6

We finalized the Project scope, including all the features we are planning on having, and the platforms and technologies we are going to use to develop our product. Product design was finalized.

Developing UI/UX Design

Week 7

The UI/ UX Design of the mobile application was developed using Figma. It contains login pages, signup pages, and dashboards for monitoring and controlling the greenhouse.

Complete Designing of Solution Architecture

Week 8

The flow of data and control were designed.

Milestone 2

Week 9

All technologies and software to be used were finalized. Testing and Security were looked into.

Presentation

CAD Design

Week 10

The Computer Aided Design (CAD) was designed and developed for the prototype of the product. All components were included.

CAD Design

Complete Full-Stack Development of Software

Week 11

Complete working front end (mobile application) and back end were developed for the software.

Presentation

Start Testing

Week 12

Testing of all the development up until now.

Cloud Development

Week 13

Development of cloud platform to host the data gained from sensors.

Milestone 3

Week 13

Full Stack was completely developed with deployment of it in AWS cloud

Presentation

Calibrating Hardware Components

Week 13

Start Testing Hardware Components Received By the Deparment while buying others from elsewhere and start calibrating the sensors we use

Start Building the Circuit

Week 14

According to the circuit diagram , the equipments were bought and circuit was connected while overcomming issues.

New
Admin

Finish Buiding the Proposed Final Prototype

Week 15

After Connecting the circuit and Connecting MicroController with Cloud, Final prototype of the product was started to Build.

Final Milestone

Week 15

New